{"id":1128,"date":"2014-08-04T11:17:44","date_gmt":"2014-08-04T15:17:44","guid":{"rendered":"http:\/\/www.nomcb.com\/?p=1128"},"modified":"2014-08-04T12:53:44","modified_gmt":"2014-08-04T16:53:44","slug":"possible-data-manipulation-inflates-mid-currituck-bridge-score","status":"publish","type":"post","link":"https:\/\/www.nomcb.com\/?p=1128","title":{"rendered":"POSSIBLE DATA MANIPULATION INFLATES MID-CURRITUCK BRIDGE SCORE"},"content":{"rendered":"<p>TO:\u00a0 NCDOT Strategic Transportation Investments Decision Makers<\/p>\n<p>I would like to thank you and the legislature for implementing the new P3.0 data driven process for transportation funding in our great state. This new process of using data removes political influences on projects and lets them stand on their own merit.<\/p>\n<p>I am a vocal critic of the Mid-Currituck Bridge project R-2576 and was very interested to see where that project landed in the P3.0 scoring process. I would finally be able to see how it truly scored against other projects vying for dwindling resources without outside interference. This project has been fraught will \u201chonest mistakes\u201d from Governor Perdue\u2019s office in 2012 among other issues of political favoritism and manipulation.<\/p>\n<p>I noticed immediately when checking the financials used in scoring this project for the new P3.0, found here,<\/p>\n<p><a href=\"https:\/\/connect.ncdot.gov\/projects\/planning\/STIData\/Highway_STI_Data.xlsm\">https:\/\/connect.ncdot.gov\/projects\/planning\/STIData\/Highway_STI_Data.xlsm<\/a>,<\/p>\n<p>that the Total Cost for the project, Construction + ROW + Utilities is listed as <strong>$410,820,000<\/strong>, <strong>NOT<\/strong> The current July 2014 STIP Total Cost of <strong>$639,512,000, <\/strong>which is calculated in the same manner, Construction + Utilities + R.O.W. = Total Cost. See current S.T.I.P. here:<\/p>\n<p><a title=\"July 2014 State Transportation Improvement Program\" href=\"https:\/\/connect.ncdot.gov\/projects\/planning\/Planning%20Document%20Library\/LIVE_STIP.pdf\" target=\"_blank\">https:\/\/connect.ncdot.gov\/projects\/planning\/Planning%20Document%20Library\/LIVE_STIP.pdf<\/a> <strong>.<\/strong><\/p>\n<p>\u201cOther Funds\u201d should <strong>NOT<\/strong> be used to lower the Construction Cost, only the Total Cost to calculate the Cost to NCDOT. So it is obvious that <strong>someone entering the data for this project, subtracted $237,516,000, the amount of \u201cother available funding\u201d,<\/strong> <strong>from the Construction Cost, and then subtracted, \u201cOther Funds\u201d AGAIN, from the artificially lowered project \u201cTotal Cost\u201d, to obtain the exceptionally low \u201cCost to NCDOT\u201d, which is used in calculating the Cost\/Benefit Analysis for the project. <\/strong>These <strong>\u201cmistakes\u201d<\/strong> lower the Total Cost and the Cost to NCDOT by $237,516,000, which artificially inflates the score for the project. These \u201cmistakes\u201d also keep the Cost to NCDOT lower than the $200,000,000 threshold for a project before it may be subject to a \u201cCorridor Cap\u201d.<\/p>\n<p>Unfortunately it looks like the folks that favor the bridge have tried to pull a fast one again on this polluted project. I hope you are able to get to the bottom of this after all of the hard work that everyone has done to insure that the data is correct and reliable.<\/p>\n<p>I would have thought that this project, that most see as the \u201cposter child\u201d for the reasons for the new P3.0 is being implemented, would absolutely be true and accurate.<\/p>\n<p>Respectfully,<\/p>\n<p>Jennifer Symonds<\/p>\n","protected":false},"excerpt":{"rendered":"<p>TO:\u00a0 NCDOT Strategic Transportation Investments Decision Makers I would like to thank you and the legislature for implementing the new P3.0 data driven process for transportation funding in our great state. This new process of using data removes political influences on projects and lets them stand on their own merit. I am a vocal critic [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[1],"tags":[],"class_list":["post-1128","post","type-post","status-publish","format-standard","hentry","category-uncategorized"],"aioseo_notices":[],"_links":{"self":[{"href":"https:\/\/www.nomcb.com\/index.php?rest_route=\/wp\/v2\/posts\/1128","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.nomcb.com\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.nomcb.com\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.nomcb.com\/index.php?rest_route=\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/www.nomcb.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=1128"}],"version-history":[{"count":4,"href":"https:\/\/www.nomcb.com\/index.php?rest_route=\/wp\/v2\/posts\/1128\/revisions"}],"predecessor-version":[{"id":1133,"href":"https:\/\/www.nomcb.com\/index.php?rest_route=\/wp\/v2\/posts\/1128\/revisions\/1133"}],"wp:attachment":[{"href":"https:\/\/www.nomcb.com\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=1128"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.nomcb.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=1128"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.nomcb.com\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=1128"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}